Title
Approval for the Mayor and/or City Administrator to sign a contract amendment with Applied Management Engineering, Inc. (AME) in the amount of $60,049, for Phase II of the Facilities Condition Assessment for the City of Roswell.
Administration and Finance
Body
Item Summary:
AME performed the Phase I Facility Condition Assessment for 33 of the City facilities. Phase II is for the remaining 44 facililties in the amount of $60,049. The scope of work includes assessment of the structural and aesthetic condition of the facilities.
Committee or Staff Recommendation:
On November 9, 2009 the Administration and Finance & Recreation and Parks Committee recommended placing this item on the November 16, 2009 Mayor and Council Agenda.
Financial Impact:
Funding is available in Cost Center 1520CP, Account 541300 and Project 09ADM008 - City-wide Facilities Maintenance.
Presented by:
Michael Fischer, Deputy City Administrator