Roswell, GA
File #: 10-0476    Version: Name: MARTA Offset: Sidewalk Gap Closure Batch 2
Type: General Item Status: Passed
File created: 7/13/2010 In control: Mayor and City Council
On agenda: 8/9/2010 Final action: 8/9/2010
Title: Approval to award a design contract to Gresham Smith & Partners in the amount of $41,260 for the Sidewalk Gap Closure - Batch #2 project. Transportation

Title

Approval to award a design contract to Gresham Smith & Partners in the amount of $41,260 for the Sidewalk Gap Closure - Batch #2 project.

Transportation

Body

Item Summary:

The Atlanta Regional Commission programmed $25 million of MARTA capital funds in return for funding MARTA Operations in 2009. The City of Roswell is eligible to program $1,674,500 in capital improvements that enhance or augment the existing MARTA bus service in the City of Roswell. An Intergovernmental Agreement (IGA) was executed for this project.  

 

This project will design sidewalks to fill six gaps on Mansell Road, Mill Street, SR120/Marietta Highway, and Atlanta Street (SR9).

 

Committee or Staff Recommendation:

On July 28, 2010 the Community Development & Transportation Committee recommended placing this Item on the August 9, 2010 Mayor and Council Agenda.

 

Financial Impact:

Funds in the amount of $924,500 are available in the MARTA Fund Grant Cost Center. Cost Center 5540G1, Account #541415, Project #10TRA007.

 

Presented by:

Steven D. Acenbrak, P.E., LEED AP, Director of Transportation