File #: 10-0251    Version: Name: Plumbing fixtures at jail
Type: General Item Status: Passed
File created: 4/15/2010 In control: Mayor and City Council
On agenda: 5/17/2010 Final action: 5/17/2010
Title: Approval for the Mayor and/or City Administrator to sign a contract with P.E. Structures/Artlantic, Inc. to replace plumbing fixtures in the Detention Center in the amount of $49,750. Public Safety
Title
Approval for the Mayor and/or City Administrator to sign a contract with P.E. Structures/Artlantic, Inc. to replace plumbing fixtures in the Detention Center in the amount of $49,750.  
Public Safety
Body
Item Summary:
Invitation to bid # 10-084-M was issued and five bids were received ranging from $49,750 to $73,500.  P.E. Structures/Artlantic, Inc. was the lowest responsive, responsible bidder in the amount of $49,750.  The scope of work is for the demolition, replumbing and replacement of existing plumbing fixtures in the Detention Center.  The City is replacing older porcelain fixtures with stainless steel for safety and durability.
 
Committee or Staff Recommendation:
On May 4, 2010 the Public Safety & Public Works Committee recommended placing this item on the May 17, 2010 Mayor and Council Agenda.
 
Financial Impact:
$81,609.72 is approved and available for this project in the FY10 Capital Project Budget as item 09POL001, 3210CP-542300.
 
Presented by:
Ed Williams, Chief of Police