09-0371
| 1 | 1. | Minutes Approval | General Item | Approval of April 20, 2009 Mayor and Council Minutes.
Administration | Approved | Pass |
Action details
|
09-0292
| 2 | 3. | Self-motorized Asphalt Paver | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with Reynolds-Warren Equipment Company, Inc. for the purchase of a used Self-Motorized Asphalt Path Paver and approval of Budget Amendment 4210CP 05-04-09 to reallocate funds in the amount of $45,000 for the purchase.
Transportation | Approved | Pass |
Action details
|
09-0358
| 1 | 1. | HDIM O9 Proclamation | Proclamation / Recognition | Reading of a Proclamation for Heritage Days in May. | Recognized | |
Action details
|
09-0375
| 1 | 2. | Queen of Angels Presentation | General Item | Presentation by Queen of Angels Catholic School Team - Odyssey of the Mind. | Recognized | |
Action details
|
09-0256
| 1 | 3. | Memorial Day Presentation | Proclamation / Recognition | Presentation by the Roswell Memorial Day Committee.
Presented by Joe Glover, Director | Recognized | |
Action details
|
09-0341
| 1 | 4. | KRB Recognition of Award Winners | Proclamation / Recognition | Recognition of the 2009 Keep Roswell Beautiful special award honorees.
Presented by Stuart Moring, Director | Recognized | |
Action details
|
09-0324
| 1 | 5. | Fed. Approps. FY10 | General Item | Approval to submit proposals for the FY10 Federal Appropriation Requests seeking Federal funds for selected local projects.
Presented by Stuart Moring, Director | Approved | Pass |
Action details
|
09-0299
| 2 | 6. | Sidewalk Connectivity | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with Mulkey Engineering and Consultants to complete the design of three (3) Sidewalk Connectivity Projects in the amount of $61,154.10.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|
09-0312
| 1 | 7. | Crabapple/Chaffin Construction Project | General Item | Approval of Budget Amendment G806-05-04-09 to recognize revenues and corresponding construction expenditures from the Georgia Department of Transportation (GDOT) in the amount of $398,822.16 for the Construction Contract of the Crabapple Road at Chaffin Road Intersection Improvement Project.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|
09-0313
| 1 | 8. | Oxbo Road Intersection Improvement Project | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with Mulkey Engineers and Consultants for engineering services for the Oxbo Road realignment in the amount of $42,430; and approval of Budget Amendment 4210CP-05-04-09 to fund this project.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|
09-0285
| 2 | 9. | Resurfacing - Blount | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with Blount Construction Company, Inc. for the resurfacing of various streets in Roswell, in the amount of $1,737,115.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|
09-0287
| 2 | 10. | Bridge Maintenance - Sunbelt | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with Sunbelt Structures, Inc. to complete the Bridge Maintenance Contract in an amount not to exceed $409,080.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|
09-0290
| 2 | 11. | Steeplechase Trail | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with Ace Grading, for the construction of the Steeplechase Multiuse Trail Project in the amount of $91,045.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|
09-0291
| 2 | 12. | URS - SR9 - ATMS Project | General Item | Approval to authorize the Mayor and/or City Administrator to sign a contract with URS to complete the design of the SR9 Advance Traffic Management System (ATMS) Project in the amount of $132,537.
Presented by Steve Acenbrak, Director | Approved | Pass |
Action details
|