Title: Consideration to award a contract to Mulkey Engineers & Consultants in the amount of $50,180.35 for MARTA Offset Project Sidewalk Gap Closure - Batch #5
Attachments: 1. MARTAOffsetFunds_RevisedFigure3
Date Ver.Action ByActionResultAction DetailsMeeting Details
No records to display.

Title

Consideration to award a contract to Mulkey Engineers & Consultants in the amount of $50,180.35 for MARTA Offset Project Sidewalk Gap Closure - Batch #5

 

Body

Action Required:

Agenda Vote

 

Description:

The Atlanta Regional Commission programmed $25 million of MARTA capital funds in return for funding MARTA Operations in 2009. The City of Roswell is eligible to program $1,674,500 in capital improvements that enhance or augment the existing MARTA bus service in the City of Roswell. An Intergovernmental Agreement (IGA) was executed for this project in the amount of $924,500 for design and construction.

 

This project will design a sidewalk to fill a gap along the north side of Pine Grove Road, between North Coleman Road and just east of Coleman Road. Crosswalk improvements will be made at the intersection of Pine Grove Road at Coleman Road. Revised Figure 3 shows this location as #45.

 

Comments:

Funds in the amount of $729,297.20 are approved and available in Cost Center 5540G1, Account #541415, Project #10TRA007, Project Marta Offset Funds - Pedestrian Improvements.