File #: 14-0234    Version: 1 Name: Change Order, Jacobs Contract for WTP re Const. Mgmt.
Type: General Item Status: Passed
File created: 5/12/2014 In control: Mayor and City Council
On agenda: 5/28/2014 Final action: 5/28/2014
Title: Approval for the Mayor and/or City Administrator to sign a Change Order to the Jacobs Engineering Group, Inc. contract for Construction Management Services related to the construction of the Water Treatment Plant (WTP) in the amount of $188,754. Presented by Stuart Moring, Director of Public Works/Environmental
Title
Approval for the Mayor and/or City Administrator to sign a Change Order to the Jacobs Engineering Group, Inc. contract for Construction Management Services related to the construction of the Water Treatment Plant (WTP) in the amount of $188,754.
Presented by Stuart Moring, Director of Public Works/Environmental
Body
Item Summary:
Previously, Jacobs was selected to provide engineering design services for the new WTP.  Limited construction phase services were included in Jacobs' original contract for design services.  The supplemental construction services support supplied by Jacobs and detailed in this change order is essential to the project and will support the City in construction management, site observation and engineering services.  In addition to Jacobs' services, two city staff members will have major oversight roles on the WTP construction as part of the Construction Management Project Team.
Committee or Staff Recommendation:
On May 13, 2014 the Public Safety and Public Works Committee recommended placing this Item on the May 28, 2014 Mayor and Council Agenda.
Financial Impact:
Funding for the WTP Construction Management Services for this Change Order for Jacobs is available in the Water Treatment Plant Project Org 50544300, Object 541300, Project 80010 for $188,754.
Presented by:
Stuart A. Moring, P.E., Director of Public Works/Environmental