Item Summary:
Background
The applicant is requesting to renovate the façade as well as make site improvements including landscaping to an existing car dealership. The property is currently zoned CH. The application meets all zoning requirements.
Attachments
Site plan, landscape plan, elevations, and application.
Applicant will bring color and material samples to the meeting per the DRB application.
Department Comments
Engineering: No comment.
Arborist:
· Comply with UDC Section 10.2.6 Parking Lot Landscaping and Section 10.2.7 Landscape Strips.
· Comply with UDC Section 12.1.5 Minimum Tree Density.
Transportation:
· GDOT permit is required for proposed improvements along SR 9/Alpharetta Hwy prior to issuance of the Land Disturbance Permit.
· Upgrade all ADA ramps along SR 9/Alpharetta Hwy site frontage with the latest GDOT ADA ramp standard.
· Where necessary along SR 9/Alpharetta Hwy frontage, remove and replace all deteriorating sidewalk. Provide sidewalk connectivity between the building and Alpharetta St/SR 9.
· Verify ingress/egress (or driveway throat length) of the proposed driveway along SR 9/Alpharetta Hwy is minimum 25' long, measured from the right-of-way line to the outer edge of the interior drive or parking space with direct access to such drive as measured perpendicular from the street.
· Provide a trailer turn patch for car delivery trailer.
· In lieu of improvements along Sun Valley Drive frontage and Sun Valley Dr @ SR 9, meet with the City of Roswell Transportation department to discuss and resolve potential conflict with the future City of Roswell roadway improvements at that location. These issues include but are not limited to: Required right-of-way and easement for the City of Roswell project; Required right-of-way abandonment for the Honda Carland project; Drainage issues. To schedule the meeting, contact Rob Dell-Ross at 770-594-6292 or rdellross@roswellgov.com. Schedule the meeting prior to Plat Combination and/or LDP approval.
· Comments: After receiving the Land Disturbance Permit, obtain right-of-way encroachment permit from Transportation Department utility coordinator John Wooten at 770-594-6108 (direct) 6420 (Main)
Fire:
· There is one area near a retaining wall that does not appear to have a 50' outside and 30' inside turning radius. All turning radius must be 50' outside and 30' inside.
· A fire flow test must be conducted in accordance with the 2012 edition of the International Fire Code and appendix B. The total GPM at 20 PSI residual must be calculated using a 24 static test. The lowest available static pressure must be used in the calculation of the total GPM available at 20 PSI residual. ALL TEST CALCULATION AND DOCUMENTATION MUST BE INCLUDED IN THE LDP. Including the 24 static test.
· Hydrant locations must be in accordance with appendix C.
Building: No comment.
Environmental: The approval should not be considered an approval for any aspect of stormwater infrastructure.
Recommendations
Staff recommends that this applicant be approved with the condition that staff comments be resolved before submittal of LDP.
Staff Report:
Kevin Turner, Planner II
Presented by: