Title
Approval to modify the design contract with Clark Patterson Lee for the MARTA Hembree Road Multiuse Path Project in the amount of $27,455.
Transportation
Body
Item Summary:
The current project begins at Upper Hembree Road and extends eastward to the Hembree Springs Elementary School driveway. The extension of the multiuse path eastward along the school frontage to the intersection of Elkins Road would connect the trail to the Hembree Park entrance. This will complete a section of the "Purple Loop", a subset of the overall Roswell Loop system. This contract modification will increase the contract from $55,955 to $83,410.
Committee or Staff Recommendation:
On October 26, 2011 the Community Development and Transportation Committee recommended placing this Item on the November 14, 2011 Mayor and Council Agenda.
Financial Impact:
Funds in the amount of $328,699.60 are approved and available in the MARTA Offset Funds - Pedestrian Improvements grant account: Cost Center 5540G1, Account #541415, Project #10TRA007. Upon approval $301,244.60 will be remaining in Project #10TRA007.
Presented by:
Steven D. Acenbrak, PE, LEED AP, Director of Transportation