Roswell, GA
File #: 12-0056    Version: Name: Recycling Ctr. Mezzanine Proj.
Type: General Item Status: Passed
File created: 2/14/2012 In control: Mayor and City Council
On agenda: 2/27/2012 Final action: 2/27/2012
Title: Approval for the Mayor and/or City Administrator to sign a contract with C.B. Summer Construction Co., Inc. for completion of the second floor of the Recycling Center in the amount of $67,228.99.
Attachments: 1. Recycling Center - #2 Warehouse crew Leaders office - operating floor, 2. Recycling Center - #4 2nd Floor as it is now, 3. Recycling Center - #5 2nd Floor as it is now
Title
Approval for the Mayor and/or City Administrator to sign a contract with C.B. Summer Construction Co., Inc. for completion of the second floor of the Recycling Center in the amount of $67,228.99.
Body
Item Summary:
Invitation to Bid #12-034-B was issued and eighteen (18) bids were received ranging from $67,228.99 to $123,000.  C. B. Summer Construction Co., Inc. was the lowest responsive, responsible bidder in the amount of $67,228.99.  This project will complete the original design creating three offices, two storage closets, and a small conference area.
 
Committee or Staff Recommendation:
On February 14, 2012 the Public Safety and Public Works Committee recommended placing this item on the February 27, 2012 Mayor and Council Agenda.
 
Financial Impact:
Funds in the amount of $115,000 are approved and available for this project in Cost Center 455A, Account #541300, Project #12ENV025.  Upon approval $47,771 will be remaining in the project.
Presented by:
Stuart A. Moring, P.E., Director of Public Works/Environmental