File #: 13-0373    Version: 1 Name: Spring Dr. Waterline BA
Type: General Item Status: Passed
File created: 8/12/2013 In control: Mayor and City Council
On agenda: 8/26/2013 Final action: 8/26/2013
Title: Approval of Budget Amendment #50544400-08-26-13 in the amount of $70,000 to increase the Spring Drive Waterline Replacement Project Budget from $350,000 to $420,000. Public Works/Environmental
Attachments: 1. ATTACHMENT SPRING DR. WATER LINE REPLACEMENT AREA FINAL.pdf
Title
Approval of Budget Amendment #50544400-08-26-13 in the amount of $70,000 to increase the Spring Drive Waterline Replacement Project Budget from $350,000 to $420,000.  
Public Works/Environmental
Body
Item Summary:
The Spring Drive Waterline Replacement Project includes the southern half of Spring Drive (south of Hillcrest Drive).  The northern half of construction is planned for FY2015.
Designers have recommended that the project be split differently, to include Hillcrest Drive construction in Phase 1.  Accordingly, the construction cost estimates from the City On-Call Construction Contractors are above the $350,000 budgeted amount.  The additional $70,000 will cover the new project estimate of approximately $405,000 for the engineering oversight required and will allow for a contingency.
 
Committee or Staff Recommendation:
On August 13, 2013 the Public Safety and Public Works Committee recommended placing this Item on the August 26, 2013 Mayor and Council Agenda.
Financial Impact:
Funding in the amount of $350,000 is approved in the FY 2014 Budget for the Spring Drive Waterline Replacement Project.  Currently $148,000 is budgeted for a waterline project on Atlanta Street and this project will not be completed this year; therefore, the funds are available to redistribute to the Spring Drive Waterline replacement project.  Upon approval of Budget Amendment 50544400-08-26-13, funds in the amount of $70,000 will be transferred from the Atlanta Street 12-Inch Ductile Iron Water Main Project, Org 50544400, Object 541420, Project 80038.  The new FY2014 project budget for the Spring Drive Waterline Replacement project will be $420,000 in Org 50544400, Object 541420, Project 80037.
Presented by:
Stuart A. Moring, P.E., Director of Public Works/Environmental