Title
Approval of a change order to the Corps of Engineers for additional costs for the installation of the well house, water treatment system, and distribution line in the amount of $51,000.
Presented by Stuart Moring, Director of Public Works/Environmental
Body
Item Summary:
The City of Roswell entered into an agreement with the Corps of Engineers to build a well water treatment facility. The bids for the work from the bidding contractors were higher than the original estimated cost. The original authorized amount of Roswell's share of the cost was $326,000 and the estimated portion of Roswell's share of the cost based on the bids is $377,000.
Committee or Staff Recommendation:
On October 11, 2011 the Public Safety and Public Works Committee recommended placing this Item on the October 24, 2011 Mayor and Council Agenda.
Financial Impact:
$187,619 is approved and available for this project in Cost Center 440B, Account #541200, Project #08ENV016-Groundwater Supply Options.
Presented by:
Stuart A. Moring, P.E., Director of Public Works/Environmental