Skip to main content
Roswell, GA
File #: 14-0210    Version: 1 Name: Approval of RES to sign PFA with GDOT and accept $95,980
Type: General Item Status: Passed
File created: 5/1/2014 In control: Mayor and City Council
On agenda: 5/12/2014 Final action: 5/12/2014
Title: Approval of a Resolution to sign a Project Framework Agreement (PFA) with the Georgia Department of Transportation (GDOT) for the SR 140/HBR at Warsaw Road Intersection improvement construction in the amount of $95,980. Transportation
Attachments: 1. 15 - To Accept Project Framework Agreement with GDOT for SR 140_HBR at Warsaw Road intersec imprvmts_051214, 2. HBR-Warsaw Construction Agreement (2), 3. RESOLUTION_Accept_PFA 2014 05-12-14
Title
Approval of a Resolution to sign a Project Framework Agreement (PFA) with the Georgia Department of Transportation (GDOT) for the SR 140/HBR at Warsaw Road Intersection improvement construction in the amount of $95,980.
Transportation
Body
Item Summary:
This project consists of extending the westbound left-turn lane along SR 140 approximately 240 feet and modifying the median noses to improve the left turn radius. This is a GDOT funded operational improvement project and was identified in the HBR Corridor Study as short-term project #6.  Roswell will provide local oversight of construction.  
 
GDOT requires the City to sign a GDOT Construction Agreement before a notice to proceed is issued to a contractor. The agreement stipulates the GDOT will reimburse the City for construction costs up to $95,980.  
 
Committee or Staff Recommendation:
On April 30, 2014 the Community Development and Transportation Committee recommended placing this Item on the May 12, 2014 Mayor and Council Agenda.
 
Financial Impact:
Total construction cost for the intersection improvement is $95,980, for which the City will be reimbursed completely by GDOT.  Funding for this project is available in Org 22142200, Object 541415, and Project 91010.
 
Presented by:
Steven D. Acenbrak, PE, LEED AP, PWLF, Director of Transportation