Roswell, GA
File #: 11-0481    Version: Name: Change order to Crabapple Sidewalk construction Contract
Type: General Item Status: Passed
File created: 7/19/2011 In control: Mayor and City Council
On agenda: 8/8/2011 Final action: 8/8/2011
Title: Approval of a change order to JJE Constructors, Inc. for the Crabapple Sidewalk Project in the amount of $37,377.20.

Title

Approval of a change order to JJE Constructors, Inc. for the Crabapple Sidewalk Project in the amount of $37,377.20.

Body

Item Summary:

This change order is the result of an increase in the height of the wall for safety, a guardrail relocated to save trees, and other contract changes due to field conditions. This change order will bring the new construction contract amount to $216,941.07.

 

Committee or Staff Recommendation:

On July 27, 2011 the Community Development and Transportation Committee recommended placing this Item on the August 8, 2011 Mayor and Council Agenda.

 

Financial Impact:

Funds of $197,529 are approved and available in the 2000 Bond Sidewalk Connectivity Project, Cost Center 9810, Account #541415, Project #06TRA001.  Upon approval $160,151.80 will be remaining.

 

Presented by:

Steven D. Acenbrak, PE, LEED AP, Director of Transportation