Approval for the Mayor and/or City Administrator to sign a construction contract with Summit Construction & Development, LLC for the Holcomb Bridge Road Multi-Use Trail in the amount of $681,557.40.
Presented by Steve Acenbrak, Director of Transportation
Body
Item Summary:
Invitation to Bid #13-234-C was issued and eleven (11) bids were received with costs ranging from $681,557.40 to $1,142,515.66. Summit Construction & Development, LLC was the lowest, responsive responsible bidder in the amount of $681,557.40.
The project consists of constructing approximately 7,000 linear feet of 5-inch thick concrete path along the south side of Holcomb Bridge Road from Steeplechase Drive West to South Holcomb Bridge Way. The width varies mainly from eight feet (8') to ten feet (10'). The project includes approximately 160 linear feet of 4-inch thick/5-foot wide concrete sidewalk on the Holcomb Bridge Middle School property which will connect to the trail.
Committee or Staff Recommendation:
On September 10, 2013 the Administration, Finance, Recreation and Parks Committee recommended placing this Item on the September 23, 2013 Mayor and Council Agenda.
Financial Impact:
Funds in the amount of $1,500,000 are approved and available in the Holcomb Bridge Road Multi-Use Trail Project, ORG 31242101, OBJ 541415, Project 92011.
Presented by:
Steven D. Acenbrak, PE, LEED AP, Director of Transportation