Title
Approval of a change order to URS for the SR 140/SR 92 Advanced Traffic Management Systems (ATMS) project to perform additional design work for the project in the amount of $70,730.
Transportation
Body
Item Summary:
The City received additional funds from the State Road and Tollway Authority (SRTA) for design and construction of the SR 140/SR 92 ATMS project. The additional funding will address:
• Traffic monitoring devices
• Adaptive Traffic Signal Control System
• Travel Time Stations
A change order in the amount of $70,730 is necessary to complete the additional design work.
Committee or Staff Recommendation:
On August 24, 2011 the Community Developement and Transportation Committee recommended placing this Item on the September 12, 2011 Mayor and Council Agenda.
Financial Impact:
Funds in the amount of $531,000 are approved and available in Project: CMAQ - SR140 ATMS: Cost Center 4272G, Account #541415, Project #08TRA005. This additional design work is funded at 100% for design and construction by SRTA (no local match required).
Presented by:
Steven D. Acenbrak, PE, LEED AP, Director of Transportation