Roswell, GA
File #: 11-0686    Version: 1 Name: Supplemental Agreement with Urey for Medians - $31,227.62
Type: General Item Status: Passed
File created: 11/3/2011 In control: Mayor and City Council
On agenda: 11/14/2011 Final action: 11/14/2011
Title: Approval for the Mayor and/or City Administrator to sign a Supplemental Agreement for the Midtown Streetscape Project with Urey Companies in the amount of $31,227.62. Transportation
Attachments: 1. Supplemental Agreement for Urey Companies - Alpharetta Street Improvements

Title

Approval for the Mayor and/or City Administrator to sign a Supplemental Agreement for the Midtown Streetscape Project with Urey Companies in the amount of $31,227.62.

Transportation

Body

Item Summary:

The Georgia Department of Transportation (GDOT) asked the City to provide a Supplemental Agreement to amend the Midtown Streetscape contract between the City and Urey Companies for the construction of three additional raised medians along SR9.  The total cost for the three additional medians is $31,227.62.  The Supplemental Agreement allows GDOT to reimburse the City 80% of that additional cost.

 

Committee or Staff Recommendation:

On October 26, 2011 the Community Development and Transportation Committee recommended placing this Item on the November 14, 2011 Mayor and Council Agenda.

 

Financial Impact:

Funds in the amount of $46,332.55 are approved and available in the Midtown Streetscape Project: Cost Center 4210CP, Account #541415, Project #05TRA007 to cover the City's 20% share.

 

Presented by:

Steven D. Acenbrak, PE, LEED AP, Director of Transportation