Title
Approval to award a contract to Blount Construction for the 2014 Citywide Resurfacing Project in the amount of $1,069,320.
Presented by Steve Acenbrak, Director of Transportation
Body
Item Summary:
Invitation to bid #14-058-C was issued and nine bids were received ranging from $1,069,320 to $1,477,815.90. Blount Construction was the lowest responsive, responsible bidder for this project in the amount of $1,069,320.
The project consists of patching, milling, leveling, resurfacing and restriping various roads throughout the City. Construction should begin in May 2014 and should be completed within 180 calendar days, weather permitting.
Committee or Staff Recommendation:
On March 26, 2014 the Community Development and Transportation Committee recommended placing this Item on the April 14, 2014 Mayor and Council Agenda.
Financial Impact:
Funds in the amount of $2,718,780.66 are approved and available in the Resurfacing project account, ORG 35042200, OBJ 522205, Project 90001
Presented by:
Steven D. Acenbrak, PE, LEED AP, PWLF, Director of Transportation