Attachments: 1. Application, 2. Flood Insurance Rate Map, 3. Site Plan, 4. Tree Density Plan, 5. Plant List, 6. Land Surveying, 7. Site Plan, 8. 1st Floor Dimension Plan, 9. South Proposed Elevations, 10. East & West Proposed Elevations, 11. North Elevations, 12. Grading & Drainage Plans, 13. Tree Replacement Plans, 14. Landscape Plan, 15. Site Photos, 16. 09090032 - 1500 HBR PW&Env comments letter, 17. Staff Report, 18. Grading & Drainage C-4, 19. South Elevations A4-10a, 20. A4-10b, 21. Tree Replacement Plan, 22. Landscape Plan L1-11, 23. Staff Report, 24. 10-6-09 Minutes, 25. Approval Letter

Title

DRB09-41, 1500 Holcomb Bridge Road, Georgia Commerce Bank

Body

Staff Report:

The Design Review Board made the following comments at their October 6, 2009 meeting:

 

• Choose a lighter color for the building and bring a few options to the next meeting

• Bring a sample of the existing color to the next meeting

• Work with staff on bio-retention and parking options

 

The applicant has responded by submitting a revised site plan and landscape plan that reflect the addition of a bio-retention cell and elevations showing a different color for the building.

 

The subject property is on 1.509 acres located at 1500 Holcomb Bridge Road. The property is currently zoned C-3 (Highway Commercial District).

 

The vacant property was previously a furniture store, but is being proposed as a medical office building. The building is two stories and has a total of 22,025 square feet. To accommodate the parking requirements for medical office use, the applicant has been approved for a variance for encroaching on the landscape strip fronting Holcomb Bridge Road and proposes a reconfiguration of the parking lot. The applicant is also proposing the following exterior changes to the building:

 

• The removal of the existing entry portico

• The new entry feature will be constructed of EIFS to match the rest of the existing building

• The entire building will be painted in neutral colors

 

Presented by:

James Baldwin, Planner II