Approval for the Mayor and/or City Administrator to sign a contract with Frank Suddeth & Sons, Inc. for the emergency repair of stormwater pipes at Chattahoochee Street in the amount of $31,835.
Presented by Stuart Moring, Director
Body
Item Summary:
The culvert and stormwater pipe at 365 Chattahoochee Street have been damaged and are failing due to the flooding rains on September 21, 2009. The emergency repair is necessary to prevent further erosion, pipe failure and potential road collapse. The contractor provided a reasonable estimate for the scope of work to be completed and was available immediately for the repair.
Committee or Staff Recommendation:
This item meets the "special emergency exceptions" provision in Section 2.7.19(c) of the Code of Ordinances regarding the purchase of goods or services.
Financial Impact:
Funding in the amount of $64,439.11 is available in Cost Center 7110CP, Account 541200, Project # 09ENV013, Undesignated Stormwater Projects. The Chattahoochee St. Emergency Stormwater Pipe Repair costs $31,835, leaving a remaining balance of $32,604.11.