File #: 11-0480    Version: Name: Change order to Roundabout Const Contract $40,589.40
Type: General Item Status: Passed
File created: 7/19/2011 In control: Mayor and City Council
On agenda: 8/8/2011 Final action: 8/8/2011
Title: Approval of a change order to CMES, Inc. for the Grimes Bridge Road at Norcross and Warsaw Intersection Improvement Project in the amount of $40,589.40.

Title

Approval of a change order to CMES, Inc. for the Grimes Bridge Road at Norcross and Warsaw Intersection Improvement Project in the amount of $40,589.40.

Body

Item Summary:

This change order is the result of additional landscaping, paving of a driveway for an impacted property owner and other small contract changes due to field conditions. This change order will bring the new construction contract amount to $619,788.

 

Committee or Staff Recommendation:

On July 27, 2011 the Community Development and Transportation Committee recommended placing this Item on the August 8, 2011 Mayor and Council Agenda.

 

Financial Impact:

Funds of $448,837.56 are approved and available in the Grimes Bridge/ Norcross/ Warsaw Intersection Account, Cost Center 4210CP, Account #541415, Project #08TRA001.  Upon approval $408,248.16 will be remaining.

 

Presented by:

Steven D. Acenbrak, PE, LEED AP, Director of Transportation