Title
Approval to accept two Permanent Easements as part of the Holcomb Bridge Road Multi-Use Trail.
Transportation
Body
Item Summary:
Right of way negotiations are ongoing for the Holcomb Bridge Road Multi-Use Trail project.
Two signed easement agreements have recently been received from property owners. Parcel 1 is a donation of 210.21 square feet and Parcel 2 is a donation of 768.32 square feet.
This phase of the project consists of an 8 to10-foot multi-use trail along the south side of Holcomb Bridge Road from Steeplechase Road to the Holcomb Bridge Middle School. The second phase continues to South Holcomb Bridge Way/Nesbit Ferry Road.
Committee or Staff Recommendation:
On April 25, 2012 the Community Development and Transportation Committee recommended placing this Item on the May 14, 2012 Mayor and Council Agenda.
Financial Impact:
N/A
Presented by:
Steven D. Acenbrak, PE, LEED AP, Director of Transportation