Title: Approval of a Resolution to sign a Construction Agreement with Georgia Department of Transportation (GDOT) for the SR 140 from SR 400 Northbound Ramps to Old Alabama Road project in the amount of $1,045,903.11 and approval of Budget Amendment 22142200-09-10-2014 in the amount of $148,878.11. Presented by Steve Acenbrak, Director of Transportation
Attachments: 1. RESOLUTION_Accept_CSTA 2014 09-10-14, 2. 0010880 Construction Agreement- NB Ramp
Title
Approval of a Resolution to sign a Construction Agreement with Georgia Department of Transportation (GDOT) for the SR 140 from SR 400 Northbound Ramps to Old Alabama Road project in the amount of $1,045,903.11 and approval of Budget Amendment 22142200-09-10-2014 in the amount of $148,878.11.
Presented by Steve Acenbrak, Director of Transportation
Body
Item Summary:
This is a traffic operational improvement project to eliminate the SR 140 eastbound left turn 'trap' lane approaching Old Alabama Road. The project will add a right turn lane to the existing SR 400 northbound ramp 7A and modify the existing traffic signal. In the westbound direction the left-turn lane to southbound SR 400 will be extended.
 
The agreement stipulates that GDOT will reimburse the City for construction costs and GDOT required materials testing up to $1,045,903.11. Roswell will provide local oversight and inspection of construction.  
 
Committee or Staff Recommendation:
On August 27, 2014 the Community Development and Transportation Committee recommended placing this Item on the September 10, 2014 Mayor and Council Agenda.
 
Financial Impact:
The original project budget was established at $1,125,000 and was based upon GDOT estimates.  Upon approval of Budget Amendment 22142200-09-10-2014, the budget will be increased by $148,878.11 based upon the actual cost of project design and construction.  
 
Total construction cost for the improvement project is $1,045,903.11 for which the City will be reimbursed completely by GDOT.  Funding for this project will be available in Org 22142200, Object 541415, and Project 91011.
 
Presented by:
Steven D. Acenbrak, PE, LEED AP, PWLF, Director of Transportation