File #: 10-0726    Version: Name: Change order for Crabapple Rucker 58,000
Type: General Item Status: Passed
File created: 10/19/2010 In control: Mayor and City Council
On agenda: 11/8/2010 Final action: 11/8/2010
Title: Approval to sign a change order to the Crabapple Road at Rucker Road Intersection Improvement Project Construction Contract with Urey Construction Company in the amount of $57,951.72. Transportation
Title
Approval to sign a change order to the Crabapple Road at Rucker Road Intersection Improvement Project Construction Contract with Urey Construction Company in the amount of $57,951.72.
Transportation
Body
Item Summary:
A change order to the construction contract in the amount of $57,951.72 is needed to complete the Crabapple Road at Rucker Road Intersection Improvement project. The change order is a result of conditions in the field being slightly different regarding  the waterline portion of the project.  This change order will bring the new construction contract amount to $671,950.72.
 
Committee or Staff Recommendation:
On October 27, 2010 the Community Development and Transportation Committee recommended placing this item on the November 8, 2010 Mayor and Council Agenda.
 
Financial Impact:
Funds of approximately $443,208.31 are approved and available in the Impact Fee Account, Cost Center 9610, Account 541415, Project #04TRA002.  Fulton County will reimburse the City $183,603.36 and the funds will be placed into the Impact Fee Fund balance to be reprogrammed for future transportation projects.
 